Jiangsu Construction Steel Siurcture Co., Ltd.

Exhaust Gas Source: The exhaust gas is generated from the primer paint booth, finish paint booth, primer drying room, and finish paint drying room.
Design Air Volume:
Primer Paint Booth: 65,000 m³/h
Finish Paint Booth: 65,000 m³/h
Primer Drying Room: 3,200 m³/h
Finish Paint Drying Room: 3,200 m³/h
Waste Gas Concentration:
Primer Paint Booth: 280 mg/m³
Finish Paint Booth: 500 mg/m³
Primer Drying Room: 2,000 mg/m³
Finish Paint Drying Room: 1,000 mg/m³
Waste Gas Components: The primary constituents include xylene, ethylene glycol butyl ether, and butyl acetate.
Process Configuration: The treatment process involves a zeolite rotor followed by a rotary valve Regenerative Thermal Oxidizer (RTO).
RTO Specifications:
Zeolite Rotor for Primer and Finish Paint Booths: 65,000 m³/h each
Rotary Valve RTO: 15,000 m³/h
Treatment Result: The treatment ensures that non-methane hydrocarbons (NMHC) do not exceed 25 mg/m³.