Inner Mongolia Heli Chemical Fiber (Group) Co., Ltd.
Featured Cases

Inner Mongolia Heli Chemical Fiber (Group) Co., Ltd.

2026-09-21

Waste gas source:

Workshop one contains two 1.5‑meter 12K pre-oxidation & carbonization production lines and a 4.2‑meter 24K pre-oxidation & carbonization production line.

Workshop two contains two 4.2-meter 24K pre-oxidation & carbonization production lines.

Workshop three contains two 4.2-meter 50K dual-layer pre-oxidation & carbonization production lines.

Waste gas composition:

The waste-gas components of each kind of production line and their concentrations are given in the following tables.

Tab. 1 Reference values for waste‑gas concentrations of the 1.5‑meter‑width production line (12K)

Component

Unit

Pre‑oxidation furnace

Low‑temperature carbonization furnace

High‑temperature carbonization furnace

HCN

kg/h

7.68-13.82

18.43-33.17

6.85-12.32

NH3

kg/h

3.29-5.92

6.14-11.06

2.28-4.11

CO

kg/h

2.19-3.95

5.84-10.50

2.17-3.90

CH4

kg/h

1.1-1.97

3.07-5.53

1.14-2.05

Tab. 2 Reference values for waste‑gas concentrations of the 4.2‑meter‑width production line (24K)

Component

Unit

Pre‑oxidation furnace

Low‑temperature carbonization furnace

High‑temperature carbonization furnace

HCN

kg/h

39.00-54.00

93.60-129.61

37.44-48.14

NH3

kg/h

16.72-23.14

31.20-43.20

12.48-16.05

CO

kg/h

11.14-15.43

29.64-41.04

11.86-15.24

CH4

kg/h

5.57-7.71

15.60-21.60

6.24-8.02

Tab. 3 Reference values for waste‑gas concentrations of the 4.2‑meter‑width production line (50K)

Component

Unit

Pre‑oxidation furnace

Low‑temperature carbonization furnace

High‑temperature carbonization furnace

HCN

kg/h

63.00-105.61

151.21-253.45

56.16-94.14

NH3

kg/h

27.00-45.26

50.40-84.48

18.72-31.38

CO

kg/h

18.00-30.17

47.88-80.26

17.78-29.81

CH4

kg/h

9.00-15.09

25.20-42.24

9.36-15.69

Treatment process:

Generally, exhaust gas from the pre-oxidation furnaces and all the waste gas captured by hoods are directed to RTOs, while the high-temperature exhaust gas from the carbonization furnaces is directed to TOs.

In a workshop, for each kind of production line, there is always a spare RTO serving as a backup. There are no standby TOs.

RTO specification:

The capacities of RTOs and TOs are determined by the types of production lines. RTOs installed for 1.5-meter 12K production lines have a capacity of 30,000 m3/h, while TOs installed for these production lines have a capacity of 1,150 m3/h.

RTOs for 4.2-meter 24K production lines have a capacity of 90,000 m3/h, and the capacity of TOs for these production lines is 5,700 m3/h.

Finally, RTOs for 4.2-meter 50K production lines have a capacity of 110,000 m3/h, while TOs for these production lines have a capacity of 8,000 m3/h.

Emission limits:

The emission limits are listed in the following table.

Tab. 4 Emission Limits

No.

Waste‑gas Component

Emission Limit, mg/m³

1

NMHC

120

2

NOx

100

3

HCN

1.9